The episode examines PJM’s two proposals for managing data-center demand, the different roles they were designed to play, and the concerns regulators sent back for revision.

What was said, and where it came from

  1. PJM manages electricity transmission across Maryland and 12 other states.

  2. Federal energy regulators rejected two major proposals from PJM to manage data-center electricity demand.

  3. One proposal would have required large data centers to reduce or shut off power during electricity shortages unless they secured enough new generation to meet their needs.

  4. The second proposal would have created a special electricity auction to help ensure enough power was available for those facilities.

  5. Regulators raised concerns about how the proposals would work and who would bear the costs, sending PJM back to revise its plans.