European Energy on Two Clocks
AI
This is not advice, double check important info.
A concise briefing on near-term energy repricing and slower grid construction, treated as separate developments.
What was said, and where it came from
On the twelfth of November, Newsquawk reported that Dutch TTF was firmer by more than three euros on the day.
The report said TTF was bid as a meeting between US envoys and Russian President Putin approached.
It said Russian commentary was not constructive or favourable toward Europe.
It also said regional weather models had turned colder again, with the milder turn largely removed.
On the twelfth of November, NKT said it had manufactured and delivered specially engineered cable sections for the SuedLink project in Germany.
The sections use five hundred and twenty-five-kilovolt high-voltage direct-current technology.
Each section is more than five kilometres long in one continuous length.
The sections are for installation in the tunnel beneath the River Elbe.
The next phase is to pull the cables through the tunnel.
The cables will then be connected to the wider SuedLink power-cable system.