US natural gas: Henry Hub's October low and PJM's power news
AI
This is not advice, double check important info.
A briefing on Henry Hub's October monthly low and the reasons given for current prices, plus PJM news on gas-fired plants, a new Ohio gas project, a possibly smaller capacity procurement, and October price spikes.
What was said, and where it came from
Reuters reported on the third of November that Henry Hub monthly natural gas prices averaged a two-year low in October.
Energy Connects calls Henry Hub the US gas index.
MT Newswires reported that Henry Hub futures rose 1.5 percent to $2.90 per million BTU late on Tuesday, the third of November.
FXEmpire, in its analysis published on the third of November, says futures had fallen below $3 before trading near $2.90.
FXEmpire says natural gas remains under pressure from warm weather and ample national storage.
FXEmpire says inventories are above seasonal averages.
FXEmpire says regional deficits and LNG demand could support buying on dips near $2.70.
FXEmpire says the next storage report is due on Thursday, the fifth of November.
At a panel reported on the third of November, ADNOC's chief marketing officer, Rashid Al Mazrouei, said buyers are increasingly interested in combining Henry Hub and JKM, the Asian LNG benchmark, and since indices can move differently, a mix may help buyers manage risk.
Yahoo Finance reported on the third of November that Talen Energy guided its 2027 adjusted EBITDA about 26 percent above this year's level.
Talen's chief executive tied that outlook to strong PJM fundamentals.
Vistra's shares rose 5 percent on the third of November.
Vistra closed its Cogentrix purchase on the thirtieth of October, adding 5,496 megawatts of gas plants, 3,163 of them in PJM.
The Ohio Power Siting Board authorized construction of Chestnut Run Energy in late August.
The state Public Utilities Commission said in mid-October that the only requirement left was a pre-construction conference.
The company says it has reserved turbines and major equipment, and expects the 1,300-megawatt gas plant to begin commercial operations in 2030.
Jefferies analysts said in an October 28 note that PJM's backstop procurement could be as small as about 630 megawatts, down from the 6,800-megawatt target.
Jefferies said PJM utilities lowered their near-term large-load forecasts by 6.5 gigawatts.
A Charles River Associates analysis found PJM could face a roughly 11.5-gigawatt shortfall by 2030.
Abnormally hot fall weather hit the Midwest and East Coast in October, sending energy prices above $1,000 per megawatt-hour in PJM and MISO.