US natural gas

Gas Curtailments and PJM’s Grid Timetable

AI

This is not advice, double check important info.

The episode looks at Appalachian gas curtailments and East Daley’s winter outlook, then turns to PJM transmission projects with higher costs and later schedules.

What was said, and where it came from

  1. In its report published on the eighteenth of November, East Daley Analytics says weak local prices led Appalachian producers to shut in some wells.

  2. Regional gas production fell by two billion cubic feet a day this fall.

  3. East Daley links mild shoulder-season weather and maintenance at Cove Point LNG to reduced regional demand.

  4. The national storage surplus was seventy-five billion cubic feet on the sixth of November.

  5. East Daley’s forecast has that surplus turning into a deficit by the end of January, assuming normal weather.

  6. East Daley expects winter demand to bring most Appalachian gas back.

  7. On the eighteenth of November, PJM Inside Lines reported that PJM’s board authorized changes to the scope and cost of baseline projects in its regional transmission expansion plan.

  8. Valley Link consists of two major high-voltage transmission lines and associated substations.

  9. Its estimated cost rose from about three billion dollars in 2024 dollars to five-point-one billion dollars in 2026 dollars.

  10. The planned in-service dates for major components moved from the first of June, 2029, to dates ranging from January 2030 through May 2031.

  11. Across Exelon’s projects, costs increased by seven hundred eighty-three million dollars, bringing the updated total to one-point-six-nine billion dollars.

  12. Much of the Exelon-related work is tied to upgrades needed before the Brandon Shores and Wagner generating units in Maryland can retire.

  13. PJM says that if the upgrades are not completed in time, those units are more likely to keep running under a Reliability Must-Run arrangement, which carries higher reliability risk and additional costs.