PJM's thinning winter margin and the timing of its capacity auction
AI
This is not advice, double check important info.
PJM says it expects enough power for winter, but its reserve margins are thinning, and Exelon has asked FERC to change how far ahead PJM runs its capacity auction. EOG Resources also reported record gas volumes and a sales deal linked to JKM pricing.
What was said, and where it came from
The Dominion Post reported on the fifth of November that PJM expects enough resources to meet demand under expected conditions this winter.
PJM expects 182,426 megawatts of operational capacity to serve a forecast peak electricity demand of about 147,500 megawatts.
That peak would set a new winter record if it is reached.
PJM's all-time winter peak is 143,700 megawatts, reached on the twenty-second of January, 2025.
Reserve margins continue to tighten as demand outpaces new power supplies.
Forecast winter peak demand has risen about 7,500 megawatts, or 5 percent, since 2022.
PJM ties that growth to new load, especially data centers and other large load customers.
Demand response, which pays customers to reduce power use when requested, has been activated 15 times in 2025 and 2026, compared with eight times in the previous eight years.
PJM has emergency authority from the Department of Energy to direct data centers and other large load customers to use their backup generators as a last resort.
PJM said it has never had to use this backup generation authority.
The National Weather Service predicts a slightly warmer winter for much of the country, including all of the PJM footprint.
PJM said generator outages on the scale of Winter Storm Elliott, in December 2022, could leave the system vulnerable to power outages.
A report published on the fifth of November says Exelon has filed a complaint at FERC arguing that PJM's three-year-forward Base Residual Auction is no longer just and reasonable.
Exelon is asking FERC to order PJM to hold a prompt auction just two months before the delivery year.
EOG said on the fifth of November that its third-quarter natural gas volumes were a record 3,153 million cubic feet per day.
EOG said it entered a new long-term gas sales agreement linked to JKM pricing, starting by 2030.
EOG said the agreement lifts its premium-priced exposure across LNG feedgas contracts to more than 1 billion cubic feet per day by 2030.
EOG said it approved the expansion of its Janus gas processing plant in the Delaware Basin.